It's very rare that I make a post on a park that's still under construction but this one's 'special'. I'd heard rumblings about more terrain in East Gwillimbury over the past year.
Pretty sure this is just a concept skatepark. I haven't been able to find final design plans anywhere. |
Then I saw a post from someone who's a skatepark builder.
June 8
Then, a month later, someone working for Canadian Ramp Company, posted a drone shot to their story of the build site. There's been some ground work and looks like the bowl has been excavated.
This was posted on July 11.
I guess the good news is that there's no other CRC builds from earlier this year I'm going to find. |
I was visiting a friend in East Gwillimbury this week so I had to check it out. There's a road that runs right next to the build so after dark, we went back for a lurk.
We didn't explore the whole site but from what I saw, the bowl is excavated.
Footings poured for a hubba and a ledge. I also spotted a framed out 'Pier 7' Ledge.
So here comes some skater math.
West Shore Skate Spot was built in 6 weeks. On time and as promised.
This project is 6 weeks into to the build.
Let's say it's 3 time as large a project. So allowing 18weeks for completion, it should be done by the last week of October.
CRC is Approximately at the same point WSSS was at 15 days in.
So if my skater math is correct, they're on track, even if I think that should be way further into the project.